back to verview: 4 post lifts order information

6 post bus lift

4 post bus lift

The company HYWEMA® exchanged a more than 30 years old 6 post bus lift in the washing bay at a southern German public transportation service.  Because of strongly corroded and no longer conformed to the current requirements for low floor busses. Problem definition was to increase the capacity by 10 tons to 30 tons but to maintain the drive-on height. Thereby to increase the rail length and the internal distance between the columns.

4 post bus lift 2 6 post bus lift example A46593

To increase durability of the post bus lifts at the wet area all steal parts were galvanized. Of course the platform was professionally installed on-site and commissioned by HYWEMA® assembly operators.  Foundation work was not necessary in this case. The cabling took place within the lifting platform, only the connection to the control box fixed on the hall wall took place throug ceiling wiring.